Leon County
Board of County Commissioners

Cover Sheet for Agenda #32
 
September 15, 2026
To: Honorable Chairman and Members of the Board
  
From: Vincent S. Long, County Administrator
  
Title: First of Two Public Hearings to Adopt an Ordinance to Establish an 18-Month Moratorium on Large-Load Customer Facilities, including Large-Scale Data Centers

 

 

Review and Approval: Vincent S. Long, County Administrator
Department/Division
Review and Approval:
Ken Morris, Assistant County Administrator
Chasity H. O’Steen, County Attorney
Nawfal Ezzagaghi, Assistant County Administrator
Scott Brockmeier, Director, Development Support & Environmental Management
Lead Staff/
Project Team:
Ryan Culpepper, Director, Development Services Division
Gretchen Brantley, Assistant County Attorney
Ana Richmond, Development Services Administrator

 

 


Statement of Issue: 

This agenda item requests the Board conduct the first of two required public hearings to adopt an ordinance establishing an 18-month moratorium pausing the acceptance, review or approval of applications for development permits, development orders, rezoning, or site plans related to large- load customer facilities, including large-scale data centers, consistent with the scope of Senate Bill 484, as enacted in Chapter 2026-65, Laws of Florida, and schedule the second and final public hearing for October 13, 2026 at 6:00 p.m. 

 

Fiscal Impact: 

This item has no fiscal impact. 

 

Staff Recommendation: 

Option #1: Conduct the first of two public hearings to adopt an Ordinance establishing an 18-month moratorium on large-load customer facilities, including large-scale data centers (Attachment #1), and schedule the second and final public hearing for October 13, 2026, at 6:00 p.m. 

 

Report and Discussion 

 

Background: 

As directed by the Board at its July 14, 2026 meeting, this item requests that the Board conduct the first of two public hearings to consider an ordinance establishing an 18-month moratorium pausing the acceptance, review or approval of applications for development permits, development orders, rezoning, or site plans related to large-load customer facilities, including large-scale data centers as defined in Chapter 2026-65, Laws of Florida (“Senate Bill 484”). 

 

Senate Bill 484 became effective on July 1, 2026, and emphasizes the unique planning, infrastructure, and compatibility considerations that large-load facilities with substantial electric or other utility demands present, including large-scale data centers, and provides that such considerations and the associated impacts shall be addressed through local comprehensive planning and land development regulations.  Neither the Leon County Development Code (“Code”) nor the Tallahassee-Leon County 2050 Comprehensive Plan (“Comp Plan”) contain specific provisions addressing large-load customers or data centers of any size.  As a result, the County currently does not have a regulatory framework to evaluate the compatibility, infrastructure, and utility-demand impacts SB 484 directs be addressed through comprehensive planning and land development regulations.  This moratorium provides the time necessary for staff to develop Code and Comprehensive Plan amendments establishing such a framework prior to further applications being received, reviewed, or approved. 

 

Consistency with Senate Bill 180 (2025) 

In June 2025, the Florida Legislature enacted Senate Bill 180, enacted in Chapter 2025-190, Laws of Florida ("SB 180").  Section 28 of SB 180 applies to counties listed in the Federal Disaster Declaration for Hurricane Debby (DR-4806), Hurricane Helene (DR-4828), or Hurricane Milton (DR-4834).  Leon County is listed in the disaster declarations for Hurricanes Debby and Helene, and is therefore subject to Section 28, which through October 1, 2027, prohibits a covered local government from proposing or adopting:  a moratorium on the construction, reconstruction, or redevelopment of property damaged by a covered hurricane; a more restrictive or burdensome amendment to its comprehensive plan or land development regulations; or a more restrictive or burdensome procedure concerning the review, approval, or issuance of a site plan, development permit, or development order. 

 

To avoid conflict with Section 28, the proposed moratorium ordinance on large-scale data center development includes an exemption for any property with documented damage from Hurricane Debby or Helene.  A property that qualifies for the exemption still requires Board approval through the Planned Unit Development process.  This exemption does not establish development rights for a property or determine that a property is an appropriate location for a large-load customer or large-scale data center.  While there are no pending applications for large load customer facilities, including large-scale data centers, any application received with a qualifying exemption would remain subject to all requirements of the Code and Comprehensive Plan, including location criteria based on anticipated impacts to infrastructure and utilities and off-site impacts to neighboring properties. 

Analysis: 

On July 14, 2026, the Board directed an 18-month moratorium on the siting of large-load customer facilities, including large-scale data centers.  The moratorium temporarily pauses the acceptance, review, and approval of applicable development applications for the 18-month term.  It does not impose a permanent prohibition on large-load customer facilities or large-scale data centers, and it will not interfere with any known projects as there are no approved or pending applications for large-scale data centers.  This window gives County staff the necessary time to conduct research, gather public input, evaluate planning considerations, and ultimately bring recommended amendments to the Comprehensive Plan and Code back to the Board to protect public health, safety, and welfare.  Staff anticipates returning to the Board with these findings and recommended amendments in September 2027 to seek additional Board guidance before initiating additional public hearings for formal adoption. 

 

A key component of this evaluation is an upcoming independent study that SB 484 directs the Office of Program Policy Analysis and Government Accountability (OPPAGA) to complete.  This comprehensive study will evaluate economic development and tax revenue impacts; the consumption of land, water, and natural resources; energy use and associated rate impacts; and public health and safety.  OPPAGA must submit the study to the Governor, the President of the Senate, and the Speaker of the House of Representatives by July 1, 2027. 

 

During the June 10, 2026, City of Tallahassee Commission Meeting, City Manager Reese Goad responded to questions about whether the current utility grid could support large-scale data centers.1  He remarked that neither the Comprehensive Plan nor the City’s code permitted large-scale data centers and that the City would have to generate additional capacity in order to accommodate such a facility. 

 

This moratorium ordinance applies to property within unincorporated Leon County.  It does not apply County wide. 

 

The enactment of a moratorium requires two public hearings by the Board.  This item constitutes the first of those two hearings and requests the Board schedule the second and final public hearing for October 13, 2026, at 6:00 p.m. 

 

Notice of Public Hearing 

The public hearing has been advertised consistent with Florida Statutes (Attachment #2).  A Business Impact Estimate was also provided online as required by Florida law (Attachment #3). 

 

 

Options: 

  1. Conduct the first of two public hearings to adopt an ordinance establishing an 18-month moratorium on large-load customer facilities, including large-scale data centers (Attachment #1), and schedule the second and final public hearing for October 13, 2026, at 6:00 p.m. 

  1. Conduct the first of two public hearings and do not adopt an Ordinance establishing an 18-month moratorium on large-load customer facilities, including large-scale data centers, and do not schedule the second and final public hearing for October 13, 2026, at 6:00 p.m. 

  1. Board direction. 

 

Recommendation: 

Option #1 

 

Attachments: 

  1. Moratorium Ordinance 

  1. Legal Advertisement 

  1. Business Impact Estimate